Friday, July 30, 2010

Stonework Revealed

Since I last posted an update on the house, we have finished the earth bermed portion of the north wall and moved on to something more exciting - actual stonework. This picture is Jenn and her Dad working together on the bermed wall.

This is what it looked like after all the slipforms were removed. A hefty concrete wall. The little white circles towards the bottom of the wall are PVC sleeves we put into the wall to house things like electrical and propane lines into the house.

The inside of the bermed wall has 2 inches of insulation, the rest of the house will have six. In order to make the six inch panels, we glued three two inch panels together. We inserted the galvanized wire through them the same as we had done before. These wires tie the foam to the wall and leave a loop on the inside in order to tie on lath when the house is closed in.


When building a masonry wall, you need to pre-plan your openings quite carefully. We went with standard sized doors and windows. In order to make a hole for said openings you need to box it out. In order to make window and door boxes that would span our 18 inch walls, we tacked 1x2 pieces on the outside of 2x12 lumber. A 2x12 is actually 1 1/2 inches by 11 1/4 inches. 1x2 measures 3/4 of an inch deep making our depth a true 12 inches. That plus our six inches of foam made the 18 inches of wall.

This picture was taken while we were setting the forms. You can see the homemade insulation panels.

This is the door box in place.

We started laying up stones using the knowledge we had gained from books. The bad part of slipforming is that you can't see the work you have done until you have another level done on top of it. We used sand at the front of the forms to keep the concrete from running all the way to the front and staining all our hard work. This is Jenn applying the sand.

I'll post a more detailed account of the process later. I get into such a flurry that I often forget to take pictures. The picture below shows the window box.

This is what the stonework looks like when you take the forms off.

This is what a section of it looks like washed. We were very happy with our first attempt at slipform stone masonry. There were very few spots where the concrete had dared creep out farther than I would have liked. When all is said and done, we will do what is called "pointing". Basically, it is like grouting between the stones to leave a more finished look. We still plan to leave the stones extending beyond the mortar, but the joints will look more uniform.
I'll try not to go so long before I do another update, but building stone wall leaves me a bit tired.

Wednesday, July 14, 2010

Cast of Characters

Mike "the Mix Master" Barnhart

Becki "Portland Power" Barnhart

Jenn "Law and Mortar" Barnhart

Jared "Crack the Whip" Barnhart

Not Pictured:
Don "the Rock Pile Destroyer" Hermanson
Pat "the Hydrator" Hermanson

Sunday, July 11, 2010

We Begin Slipforming

We were finally able to go vertical on our house! We are now 16 inches up ... on 1/3 of the house. To us, it is a great victory. We started out on Friday by tying 10 foot vertical pieces of rebar to the rebar sticking out of the footing. We opted to start on the north side of the house since this side would be bermed into the earth up to the four foot level. The only downside of this is that the rocks are inside the wall rather than showing like a stone wall. That means that when we take the forms off, all we'll see is a concrete wall.

After we tied the vertical pieces on, we also tied on a horizontal piece making a rebar grid that will add support to our concrete and stone walls.

We made sure that none of the splices were anywhere near the corners, which are very structurally important.

My Mom and my Wife poked pieces of galvanized fencing wire through the insulation. The extra wire on the inside of the insulation will be embedded into the concrete, holding the insulation in place.

The loops on the inside of the wall will be used to tie on lath that we will plaster over when the house is done.

My wife had to take some time to set up the temporary 'facilities'. We bought a camping toilet that we lovingly call 'the cabana'.

After the rebar was in place (on Saturday) we bolted all the forms together and started locking them into place. We used two different methods. To keep the forms together we put a spacer in place and wrapped tie wire around two 1x2 pieces cut to 18 inches long. I used a nail to twist and therefore tighten the wires.


Method number two was some 1x4 pieces of lumber cut to 25 3/4 inches - the exact distance from the outside of one form to the outside of the other giving us 18 inches in between. We screwed them on the top to keep the forms from bowing out.

In the meantime, my Dad built these two knockouts to house some future plumbing. We oiled everything that would be touching concrete and called it a day since the temperature was in the upper 90's.

On Sunday, we were ready to start filling in the forms. We started the day using a 1:3:3 mix of concrete. One part portland cement, three parts pea rock and three parts sand. We quickly turned to a 1:2:3 mix of one part portland, two parts pea rock and three parts sand. Joe Kohler, in his book, has termed this mix 'morcrete'. It isn't quite mortar and it isn't quite concrete. It is strong yet easy to smoosh around the rocks. My parents graciously mixed all the morcrete for the first wall. The large rocks in this wall were more or less filler to save on cost.


We put in an eight hour day to fill in this section of wall. It was tiring but gratifying. And, unless we can find a way to live behind a 16 inch section of wall, it is only the beginning.

Thursday, July 1, 2010

The Big Pour!

We finally got to do our foundation pour, and I have to say that I am very satisfied with the final product. This is due, in no small part, to my cousin Josh and the crew he brought with him – Gary, Cody and Barry. I was very impressed with how well they worked together and just knew what to do. I definitely learned a lot. We started on the front end and worked our way around screeding off the masonry heater footing as planned.


Josh finished up the more difficult area that contained all the plumbing.

While Barry the hired finisher ran the power trowel ...

I installed the wall anchors.

Like I said it went well, but not without a couple incidences. The forms bowed out in one area (not a big deal) and lifted in another (a big deal). The lifted area ruins the ability to screed off of the form and retain the same grade. Josh and his team acted fast and screeded it by eyeballing it. When all was said and done, we put the four foot level on there and it was spot on. I was very impressed and grateful that they were there.

I ordered 20.5 yards of concrete and when we were done we had less than a wheelbarrow full of concrete left. I'd like to say I'm an expert estimator, but sometimes it's just better to be lucky than good. I had estimated 19.5 yards and added an extra yard to cover any errors.

We returned to the site today to check it out. The power troweled floor looks great and I can't wait to acid stain it. I'll snap a picture the next time we go out.

Next, we go vertical!

Sunday, June 27, 2010

The Big Pour ... Almost

I took Thursday and Friday off of my "day job" in order to finish up the prep work for the big concrete pour. My Dad and I worked like mad men for two days so the site would be ready for the inspector. The inspector came and we passed even though we weren't quite finished. After he left we still needed to finish up with some of the insulation and most of the rebar. But, I'm getting ahead of myself. Let me go back to the beginning of the labor intensive long weekend. I started out by installing a loop of 4" corrugated plastic drain pipe in the event we should need a radon mitigation system.

This is what it looked like all buried. One spot near the masonry heater didn't get as low as it should have, leaving a bit of a speed bump. I don't think it will matter too much, but I probably should have pulled it out and reburied it.

I began Thursday morning by laying down an 8 mil plastic vapor barrier. I had read that if moisture wicks up through a slab on grade, it can cause flooring problems. I figured the plastic was a cheap enough insurance policy. I was joined shortly after I got on site by my Dad who probably regrets he showed up at all. We spent the day sweating and cutting XPS insulation to fit in a life size game of pink tetris.

The temperatures were hot and the humidity was high which makes for miserable working conditions. Nonetheless, we got it all just about done with the help of my Mom and my Wife. And then a storm rolled through.

We waited out the rain and decided we could still get it all cleaned up and the rebar completed before the big pour on Saturday morning. My Mom and my Wife sucked up water with the shop vac for three hours while my Dad and I finished up the steel work.

My Dad cut more that 75 32" pieces of rebar to anchor the wall to the footings. He's become invaluable to the project and we very much appreciate his help.

While all that was going on, I tied all the splices together in the footings. We used three runs of 1/2" rebar (aka #4). We used a 5' piece of pipe as a cheater bar to make the bends. Once they were in place and tied together we chaired them up on old paver bricks.

By ten o'clock Friday night (picture was taken earlier) we were all ready for the pour the following morning, provided it didn't rain again. We received a lot of rain and we don't have paved roads, so there can only be so much moisture in the ground and still allow a concrete truck carrying 10 yards of concrete to drive across our land.

It didn't rain through the night ... but it did rain Saturday morning. My cousin Josh (the foreman of team concrete) and I made the decision that it was too wet. It was a hard pill to swallow, but it was probably the safe bet. We're hoping to get it done one night this week since next weekend is a holiday weekend.

Sunday, June 20, 2010

Our First Concrete Pour!

After we dug out the hole for the masonry heater footing, the next step was to insulate it and tie the rebar together. Code required us to use half inch rebar tied together six inches on center. Tying the rebar together took me a lot longer than I thought it would. It was suggested that this would be our new mantra, "well that took longer than I thought it would." The suggester was correct.


Next we had to set the form for the heater at the right level and cut the insulation to fit. The conglomeration of wood surrounding the form was my way of giving us a place to set stakes since the hole got a little wider than it needed to be.

Jenn is eagerly awaiting the use of the new mixer.

We started filling it in, one wheel barrow at a time.





Until it was full! I should leave this next part out, but I think people would know better. I calculated 41 80 pound bags of ready mix. Of course it took 44 and I had to run to the store at the end of the pour. I'll learn my lesson, eventually. By the by, we are considering marketing a new work out DVD. It's called P-lift-80-pound-bags-of-concrete-90X. Your legs and back will scream for mercy after just one session.

After the hole was full, we screeded it and I troweled it smooth.

The forecasters were predicting a storm so we tarped it heavily. It did storm ... hard. But, to my surprise the tarp held in place.

Here's the final product. The smudge is a clump of dirt that I should have removed before taking the picture. I call it focal art.

Now that we had one pour out of the way, it was time to prep for the big pour. I rented a laser transit in order to set the footing forms to the right level. That thing was slick, much easier than the old scope style. Geez, my chicken legs are really pasty! Who took that picture?!

To keep them at the right level, we drove stakes we made out of 2x4s. Thanks are owed to my Dad (for many parts of the project) for making the 24 vampire slayers with the miter saw. I am continually impressed with how much work my Dad and my Wife put into the project even though I can be a relentless task master. Relentless task master is a euphemism for what they usually call me.

Up next, the big pour!

Saturday, June 12, 2010

Progress Report

After we finished the site prep and had a base to put our foundation on, we needed a plumber. I thought I had one locked up, but he didn't call me back. After that I started calling many plumbers. I'm not sure why, but at first I couldn't get anyone to call me back. I was an inch away from getting some books from the library and doing it myself when the clouds opened up and a ray of plumberness shone down from above. All of a sudden I had four estimates to look at. There was one clear choice at the end of it all. They happened to be the lowest bid, but more importantly, they asked the most questions and I just had a gut feeling about them. So, to be ready for them we oiled and set the footing forms in order to have our proper measurements in line.

The only bad thing about the perfect plumbers was they couldn't get to it for a week. That was Mr. Murphy and his law punching me in the gut. Then, after I was standing upright again, I calmly told Mr. Murphy that I had plenty of other work to do in the meantime. So, we decided to pick rock. We took the trailer and the pickup to a friend's farm (thank you Allens!) and got a load of rocks.

During the week, the plumbers came followed by the inspectors. During that time, I decided that the foundation pour would go more smoothly if we would pour the masonry heater (did I mention our house would have a masonry heater?) footing prior to the foundation pour. I was worried that our lack of experience would show if we needed to set screed rails in order to cover the distance from one end of the house to the other. The masonry heater footing in the center of the house would give us an edge to screed off of, thus shortening the distance between screed points.

Next, I constructed the heater form, read the code book and calculated the amount of concrete it would take to make the hefty footing for the masonry heater. After we determined the location, we marked it and began digging it out.

We dug it out so that the total depth would be 12 inches. Next we need to get the rebar cut and ready. We'll put the insulation and rebar in place and use our cement mixer to pour the heater footing. After that, we'll pour the rest of the foundation.

By the by, I haven't had time to report on my hybrid poplar cuttings. I will do a full report, but for now I can report that I have approximately 225 mini hybrid poplar trees in grow bags.