Tuesday, October 26, 2010

The South Gable

After we finished all the stone work on the first floor. The only stone work left was the peak on the south side that extends up to the second floor. Due to the weather getting colder, we considered doing the peak in wood frame. Ultimately we couldn’t decide on a facing material that would equal the beauty of the stone. So stone it is. We also took a time out while the weather was warm to do some prep work on the back filling.

The peak went as fast as I expected it too, which was a comforting change to how things usually go.

We are using buckets and rope to get the rocks and concrete to the top.


The speed picked up even more after a surprise visit from my Aunt and Uncle. Thanks!




We are really racing the clock at this point. Not only are the temperatures getting colder, we also have much shorter evenings. Needless to say, we are very eager to set the last stone. We are very close to being able to put a roof on and make it weather tight.